Install 56,500 ft of 16-in dia weight-coated steel waterline from Punta Lima to Vieques, Puerto
Vieques Waterline

Install 56,500 ft of 16-in dia weight-coated steel waterline from Punta Lima to Vieques, Puerto
Onshore welding, pull 8,100 Lft of 10 in dia steel pipe with 3 in foam
Dredge burden/remove pipeline crossing in ship channel. Facilitate with crane barges and winches.
Construct/launch 60 in heat-fused intake pipeline with concrete weights.
Construct a new twin 84″ diameter RCP outfall approximately 1500 LF including on shore demolition
Install 10+ mi of 36 in pipeline across East Matagorda Bay.
Install 5,900 Lft of 122-in dia reinforced concrete pressure pipe within 20 ft wide coffer
Construct dual 48 in outfall pipelines and valve structures for new Dredged Material Placement Area.
Assemble/stage 54 in HDPE pipeline with concrete weights, install in prepared trench.